120. During the examination of the project, the Régie de l’énergie must take into account, in particular,
(1)  the project completion probability;
(2)  the positive and negative economic impact;
(3)  the pipeline design, including, in particular, the construction, use, maintenance and temporary or permanent shutdown work; and
(4)  the needs for the petroleum gathering and transportation in the territory covered by the project.
O.C. 1253-2018, s. 120.
In force: 2018-09-20
120. During the examination of the project, the Régie de l’énergie must take into account, in particular,
(1)  the project completion probability;
(2)  the positive and negative economic impact;
(3)  the pipeline design, including, in particular, the construction, use, maintenance and temporary or permanent shutdown work; and
(4)  the needs for the petroleum gathering and transportation in the territory covered by the project.
O.C. 1253-2018, s. 120.